The Stockton Avenue Rehabilitation Project in Ripon is in its final stages.
With completion targeted for this summer, D.A. Wood Construction is leading the efforts that will soon call for the laying of the concrete pavers along Stockton Avenue, from Second Street to Doak Avenue.
Packages are lined up along the roadway as surface work continues – some of the side roads have been closed to traffic during the road-grading efforts on Stockton Avenue.
The Ripon City Council heard at last month’s meeting that current state of the road was that of dirt and gravel.
Along with pavers will be the striping of the road and signage to match the aesthetics of downtown Main Street.
Another for the pavers is durability.
According to the City of Ripon website: “Due to heavy traffic along Stockton Avenue, larger pavers that are 100 millimeters in size will be utilized – to install the concrete pavers, the contractor will lay a sand layer before placing the pavers. Once the pavers are cut and placed, another layer of sand is placed between the concrete paver joints and the seal.”
Stockton Avenue, in addition, will feature signage and striping for Type III shared bike path, installing of slopes behind the new six-food wide sidewalk to match the existing elevations, and new streetlights.
Work on the Stockton Avenue Rehabilitation Project started in February 2021 shortly after D.A. Wood was awarded the contract.